3.8.3 INSTALLATION PROCEDURE
G909I500.WMF
CAUTION
Unplug the main machine power cord before starting the following
procedure.
NOTE: 1) After installing the finisher (A697) on the machine, the bridge unit for the
mailbox (G912) must be installed.
2) The bridge unit for the mailbox must be installed before installing this
unit on the main machine.
1. Unpack the finisher and remove the pieces of tape.
2. Attach the front joint bracket [A] and rear joint bracket [B] to the main machine
(2 screws each).
3. Peel off the backing of the double-sided tape that is attached to the lower
grounding plate [C].
4. Attach one lower grounding plate to the center of the bottom edge of the paper
tray unit as shown.