Figure 127: Closing the socket release lever
Ê Close the socket release lever (1) and latch it under the load plate retention
tab (2) to lock down the load plate.
Ê If applicable, install the second processor accordingly.

11.2.3 Concluding steps

"Installing processor heat sinks" on page 245
Ê
"Reassembling" on page 59
Ê
"Connecting the server to the power source" on page 64
Ê
"Updating or recovering the system board BIOS and iRMC" on page 75
Ê
"Switching on the server" on page 66
Ê
"Enabling SVOM boot watchdog functionality" on page 87
Ê
"Enabling BitLocker functionality" on page 93