Replacing A Management Blade; Required Tools; Preliminary Steps - Fujitsu Primergy BX900 S2 Upgrade And Maintenance Manual

System unit
Hide thumbs Also See for Primergy BX900 S2:
Table of Contents

Advertisement

Management Blades
9.3

Replacing a management blade

Field Replaceable Units (FRU)
average hardware task duration: 5 minutes
average software task duration: 10 minutes
9.3.1

Required tools

Preliminary and concluding steps: tool-less
Installing connection blades: tool-less
9.3.2

Preliminary steps

Before replacing a management blade, perform the following steps:
Ê If applicable, open the rack door as described in section
door" on page
Ê Locate the desired system unit as described in section
error class" on page
Ê Locate the defective management blade as described in section
the defective component" on page
The following step applies if only one management blade is installed in the
system unit.
Ê Ask the system administrator for the firmware version of the defective
management blade.
The following steps applies if two management blades are installed in the
system unit.
Ê Connect a field service terminal to the master management blade as
described in section
page
44.
146
48.
45.
"Accessing the management blade web interface" on
Upgrade and Maintenance Manual
48.
"Opening the rack
"Determining the
"Locating
BX900 S2

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents