Chapter 2 Installing the Tape Library
2.5 Rack Mounting the Tape Library
7
Mount the left rail in the same way:
In PRIMECENTER racks, put the positioning tappet of the left rail into the appropriate hole of the
•
support bracket which you have mounted on the left rear rack post.
Compress the spring mounted rail to its length, putting the preloaded screw head in the lower front
•
lug of the rail from behind into the appropriate hole of the left front rack post.
Screw on the upper lug of the front rail end to the left front rack post with one screw with centering
•
washer.
Screw on the rear rail end to support bracket with two screws with centering washers as shown
•
below.
Figure 2.10 Mounted left sliding rail (rear side)
8
Put the ETERNUS LT20 S2 from the front of the rack on the support angles of the sliding rails
and push it into the rack to the back stop.
FUJITSU Storage ETERNUS LT20 S2 LTO Library Installing, Starting Up and Maintaining
The library weighs 14 kg (without media). Most of the weight is toward the
back of the library.
CAUTION