3. Physical installation
When this is achieved, the projector is set horizontal and vertical at right angles to the screen.
Image 3-25
5. Fasten the lock nut (B) of the rigging clamps.
3.5

Suspension of the FLM projector with rigging clamps

Rigging points and rigging clamps
The carrying handle, at the bottom side of the projector, is provided with eight slots. Four slots are longitudinally (A) oriented and
four slots are transversely (B) oriented. Each slot contains a rigging point of which the position in the slot can be adjusted depending
on the size of the truss installation. The rigging clamps (C) can be attached to those rigging points, which allows an easy and fast
physical setup of the projector in a hanging configuration.
Image 3-26
Necessary tools
24 mm open ended spanner.
17 mm open ended spanner.
Necessary parts
Four rigging clamps (R820411).
Safety chains.
How to install and to use the rigging clamps ?
1. Measure the distance, center tube as reference, between the two used support bars of the truss.
X mm
Image 3-27
2. Turn the projector upside down and slide the rigging points on there place in the slots, according the measured distance and
secure this position. To release the nuts of the rigging points use a 24 mm open ended spanner. Ensure that the rigging points
are symmetrically lined up, so that the projector will hang in balance.
Warning:
Be careful while working with heavy loads.
Warning:
Always secure the rigging points after adjustment.
28