Technical service
ALWAYS unplug while servicing.
Technical maintenance and repair MUST be conducted by a qualified technician only.
A warning tag (DO NOT TURN ON! WORK IN PROGRESS!) must be placed at the switchboard
during servicing.
ALWAYS use safety googles while servicing.
7.1
Technical maintenance
To provide good and safe operation of the machine, it is a must to conduct technical
maintenance on regular basis, and operating repair, as needed.
Technical maintenance — scope of work, which goal is to maintain the machine in operable
condition during intended use.
Operating repair — scope of work, which goal is to recover the machine or its parts in case of
malfunction, and renewal of its resource.
Technical maintenance stage 1 must be conducted every 360 hours of machine's
operation.
Technical maintenance stage 2 must be conducted every 1000 hours of machine's
operation.
Operating repair must be performed as needed.
It is a must to conduct technical maintenance while performing operating repair.
7.1.1 Technical maintenance Stage 1 schedule
1. Ask the operators who work with the machine for any issues related to the machine
and its operation.
2. Ensure that the machine is installed in accordance with the installation instructions
(see section 3).
3. Visually nspect the machine to detect any faults or broken parts. Make photo as
necessary.
4. Inspect supply cord, cable plug, and wall receptacle. Pay attention to mechanical
damages, damaged insulation, and colour changes. Replace damaged components.
24

Advertisement

loading
Need help?

Need help?

Do you have a question about the Vortex Popcorn Robopop 60 and is the answer not in the manual?

Questions and answers

This manual is also suitable for:

Vpm-rm4