Commissioning
7.1.4

Remove the 120 V cable for the precommissioning mode

Preliminary requirements
Procedure
 
1. Loosen the screws of the terminals (D,
E, F) of terminal block X-1.
2. Disconnect the wires (A, B, C) from the
terminals.
3. Tighten the screws.
4. Disconnect the 120 V AC cable from
the external power supply.
5. Fully remove the cable from the
electrical system.
7.2

Prepare for commissioning

Preliminary requirements
62
Only do this procedure
when a different
procedure refers to this
procedure.
Torque screwdriver, cross
Qualified installation engineer
Danger:
Hazardous voltage
Do not commission the EVSE. Only a service engineer of the
manufacturer is qualified to commission the EVSE.