Do A Check On The Electrical Parts; Set The Precommissioning Switch - ABB HVC 200 Operation And Installation Manual

Table of Contents

Advertisement

Installation
6.4.5

Do a check on the electrical parts

Preliminary requirements
Procedure
1. Make sure that these parts on the AC plate are in the correct condition or
position. For the location of the electrical parts, refer to section 3.3.4.
6.4.6

Set the precommissioning switch

Preliminary requirements
Procedure
1. Make sure that these fuses are
serviceable:
2. Set these circuit breakers to OFF:
3. Set the precommissioning switch Q10
to the position 0. For the location of
Q10, refer to 3.3.3.
4. Energize the 120 V AC connection for
the precommissioning mode.
5. Measure the voltage before the breaker Q2. It must be 120 V AC.
6. Set the breaker Q2 to ON.
7. Set the precommissioning switch Q10 to the postion 1 (EXT).
60
Only do this procedure
when another procedure
refers to it.
Part
Fuse F10
Fuse F21
Fuse F22
Circuit breaker Q2
Only do this procedure
when another procedure
refers to it.
F10
F21
F22
Q1
Q2
Condition / Position
it conducts power
it conducts power
it conducts power
Off
EXT
INT
0
1
2
Q10
HVC 200/300/360-EN | 002