Installation
Procedure
-X4
-X6
1. Prepare ferrules for the wires that are mentioned below. Refer to section 6.3.16.
2. Connect the below listed wires from the outlets. Use the illustration above as a
reference:
6.3.8

Connect the interlock and DC guard cables to the power cabinet

Preliminary requirements
48
A
B
E
F
Outlet
Wire
1
(A) 24V DC
(B) 0V DC
2
(C) 24V DC
(D) 0V DC
3
(E) 24V DC
(F)0V DC
4
(G) 24V DC
(H)0V DC
Interlock and DC guard
cables. Refer to section
12.13.9.
-X5
RJ45
-X7
RJ45
Connect to terminal Terminal name
X4-1
X4-2
X5-1
X5-2
X6-1
X6-2
X7-1
X7-2
RJ45
C
D
RJ45
G
H
+24Vdc CP1
0Vdc gnd CP1
+24Vdc CP2
0Vdc gnd CP2
+24Vdc CP3
0Vdc gnd CP3
+24Vdc CP4
0Vdc gnd CP4
HVC 200/300/360-EN | 002