6.3.17

Connect a wire that has a ferrule

Preliminary requirements
Procedure
1. Loosen the screw of the connection on
the terminal.
2. Install the ferrule in the connection of
the terminal.
3. Tighten the screw to the correct
torque. For the specifications, refer to
section 12.4.
4. Make sure that unused wires are
protected and cannot touch metal
parts.
6.4

Precommissioning mode

6.4.1

General information

You can only start the commissioning of the power cabinet when there is
a 3 phase 480 V AC power supply from the AC power grid. If there is no
3 phase 480 V AC power supply from the AC power grid, you can set the power
cabinet in precommissioning mode to prevent condensation.
The precommissioning mode only works correctly when the Neutral wire after
the transformer is not earthed. If the Neutral wire is earthed, then contact the
manufacturer. Refer to section 1.11.
 
HVC 200/300/360-EN | 002
Installation
3
B
2
A
1
57

Advertisement

Table of Contents
loading

This manual is also suitable for:

Hvc 300Hvc 360

Table of Contents