Procedure
1. Prepare the wires:
a. Cut the wires (A), (B) and (C). Make
b. Strip the insulation from the end of
c. Attach the cable lugs to the end of
2. Attach the wires to the connectors:
Use the fasteners (F) on each connection.
3. Tighten the fasteners to the correct torque. For the specification, refer to
section 12.4.
6.3.4
Connect the AC auxiliary power cable (3 phase 480 V) in the power
cabinet
Preliminary requirements
HVC 200/300/360-EN | 002
sure that the lenght is sufficient
for connection at the connectors
(D).
the wires. Make sure that the strip
length is compatible with the cable
lugs (E).
the wires. Use the cable lug tool.
L1 wire (A) to the connector F1:1
(G)
L2 wire (B) to the connector F2:1 (H)
L3 wire (C) to the connector F3:1 (I)
Torque screwdriver, cross
Wire cutter
Wire stripper pliers
Crimp pliers
3 phase 480 V AC auxiliary
power cable. Refer to
section 12.13.2.
Ferrules
Note:
The illustration shows the terminal block X3 on the power cabinet and
the connections that are in this section.
For the specific connections, refer to the installation brief, the
installation drawing and the installation manuals of the devices
installed in the system you ordered.
For information about the part numbers of the terminals, refer to
section 12.18.
G H
D
A
Installation
F
E
I
C
B
43

Advertisement

Table of Contents
loading

This manual is also suitable for:

Hvc 300Hvc 360

Table of Contents