4

4.1 Installation Preparations

Floor Loading Capacity
The floor must be able to bear the weight of the UPS and its optional
components. In the case of rack-mounted installation, ensure that the floor can
also bear the weight of the rack.
Installation Environment
Installation Clearances
Issue 17 (2024-01-30)

Installation and Cable Connection

Do not install the UPS in a high-temperature, low-temperature, or damp place
that is beyond the technical specifications.
Keep the UPS far away from water, heat sources, and flammable and
explosive substances. Install the UPS in an environment free of dust, volatile
gas, salt, and corrosive materials. Avoid direct sunlight.
Do not install the UPS in environments with conductive metal scraps in the
air.
The optimal operating temperatures for batteries are 20–30°C. Operating
temperatures higher than 30°C shorten the battery lifespan, and operating
temperatures lower than 20°C reduce the battery backup time.
Reserve a clearance of about 100 mm based on the UPS installation
dimensions for the input and output plugs on the rear backplane of the UPS.
Reserve a clearance of at least 500 mm from the front and rear of the chassis.