UPS2000-H-(6 kVA–10 kVA)
Quick Guide
1

1.1 Installation Preparations

● A circuit breaker needs to be installed in the upstream of the UPS to facilitate
● The leakage current of the 6 kVA UPS and 10 kVA UPS is less than or equal to
● When UPSs are connected in parallel, the output parallel power cables of each
● Check the lead-acid battery voltage range: Use a multimeter to measure the
● Check the lithium battery voltage range: Hold down the button on the front

1.1.1 Site Planning

Floor Loading Capacity
Ensure that the floor can bear the weight of the UPS and its optional components.
Installation Environment
Issue 01 (2022-06-30)

Installation and Cable Connection

NO TICE
maintenance.
50 mA, respectively. When selecting an RCD, consider the leakage current of
the UPS and its downstream loads.
UPS must be at least 1 m long and the length deviation must be less than
±10%. The four cables must be connected at the remote end.
voltage between the positive and negative battery terminals. Voltage range: 9.6
V x Number of batteries to 14.4 V x Number of batteries. For example, if 20
batteries are installed, the voltage between the positive and negative battery
terminals should range from 192 V (20 x 9.6 V) to 288 V (20 x 14.4 V).
panel of the lithium battery for 5 to 10 seconds to power on the lithium battery
for the first time. After the startup wizard is complete on the app (the output
voltage is set to 240 V), use a multimeter to check that the positive and
negative voltages of the lithium battery range from 235 V to 245 V.
Do not install the UPS in a hot, cold, or damp place that is beyond the
technical specifications.