5.14.5.

Install lighting protection (optional)

When using this option, the PE wire between the Power Cabinet and the
Dual Depot Charge Box doesn't have to be installed. For more details
see section Cables connecting the Dual Depot Charge Boxes
Grounding of the Dual Depot Charge Box on Page 48.
In case the Pedestal is used, the lighting protection wire must be
connected first to the GND point of the Pedestal. See section Connecting
the PE or lighting protection wire onto the pedestal on Page 94.
Prerequisites:
Tools: wire cutter, wire stripper pliers, ferrule, crimp pliers, screwdriver
1. Loosen and remove the cable gland's (#12) nut for the PE wire.
2. Slide the cable gland's nut over the PE wire.
3. Route the PE wire (B) through gland #12 to the PE connector block X8-2. Refer to the
figure above for the preferred cable route through the cable duct inside the cabinet.
4. Shorten the PE wire to the correct length - allowing to reach the PE connector block
X8-2. Do not make the wire routing too tight or too loose.
5. Tighten the nut of the gland to secure the PE wire.
6. Strip 11 mm of the insulation from the end of the PE wire (B).
7. Crimp a ferrule (A) to the end of the PE wire (B).
8. Loosen the connector screw of the PE connector block X8-2.
9. Insert the PE wire (B) into the PE connector block X8-2.
10. Tighten the screw of the connector block with a tightening torque of 1.3 Nm.
Document: v0.4 / Document No.: TBA | Date: 11-08-2021
1x or 2x AC auxiliary power cable (in case daisy-chain option is
applied),
2x DC power cables,
1x Interlock cable,
1x Ethernet cable,
Location of the PE connector block X8-2.