SECTION 4 - MACHINE OPERATION
3.
Push Engine Start switch until engine starts.
ALLOW ENGINE TO WARM-UP FOR A FEW MINUTES AT LOW SPEED BEFORE APPLYING
ANY LOAD.
4.
After engine has had sufficient time to warm
up, push in Power/Emergency Stop switch and
shut engine off.
5.
Turn Platform/Ground Select key switch to
Platform.
6.
From Ground Control Console, pull Power/
Emergency Stop switch out.
7.
From Platform Control Console, pull Power/
Emergency Stop switch out.
4-6
8.
Push Engine Start switch until engine starts.
NOTE:
Footswitch must be in released (up) position before starter will
operate. If starter operates with footswitch in depressed position,
DO NOT OPERATE MACHINE.

Shutdown Procedure

IF AN ENGINE MALFUNCTION CAUSES AN UNSCHEDULED SHUTDOWN, DETERMINE
THE CAUSE AND CORRECT IT BEFORE RESTARTING THE ENGINE.
1.
Remove all load and allow engine to operate at low speed
for 3-5 minutes; this allows further reduction of internal
engine temperature.
2.
Push Power/Emergency Stop switch in.
3.
Turn Platform/Ground Select key switch to Off.
Refer to Engine Manufacturer's manual for detailed
information.