5.
After the cleaning process is complete, the engine will run
for approximately 5 minutes to allow the Engine and
Exhaust After Treatment (EAT) to cool down. The Indicator
Gauge will display the "Regen Complete" screen as shown
and the Emissions Temperature indicator will no longer be
illuminated.
Maintenance Standstill Cleaning Initiation Methods
Maintenance Standstill Cleaning can be started by one of two
methods, by using the Analyzer or the DPF button on the Ground
Console. All the same conditions as outlined under Standstill
Cleaning must be met.
4-10

Canceling Maintenance Standstill

Maintenance Standstill Cleaning will be stopped immediately if:
• The Platform/Ground Select switch is switched from
Ground to Platform mode
• Any function switch is enabled to perform a boom func-
tion
• The Engine is powered down
If Maintenance Standstill Cleaning is interrupted, it must be re-
initiated and the Indicator Gauge will display the "Regen Failed"
screen as shown.