I/O Integration

GM General Timing Diagrams

NOTE: A 50ms delay is suggested between each CGM signal.
NOTE: When dispensing a bead, it is recommend that the discrete trigger signal be used instead of the fieldbus
trigger signal, due to the fact of timing issues and delays.
Automation Inputs (EVR Outputs)
PLC Lockout Active
System Ready
No Alarms are Present
No Deviations are Present
No Advisories are Present
System is Parking
System is Parked
Dispense Valve is Opened
Automation Outputs (EVR Inputs)
System Enabled Request
PLC Lockout Request
Parking Request
Parking Running
Key
EVR is Parking
F
. 17:
IG
56
Tag
ID
2
System On
3
4
5
6
7
13
14
9
1
2
8
EVR State
EVR Gateway Run Park