4.1. Power Up Sequence

Always power up the Enterprise Storage/Portable Storage before powering up the Projector.
The Enterprise Storage/Portable Storage must be powered up first to be correctly identified
by the SR-1000 IMB.

4.2. Power Down Sequence

Always power down the SR-1000 and Projector with the following steps:
1. Power down the SR-1000 by using the
2. Power down the Enterprise Storage/Portable Storage attached to the SR-1000.
3. Power down the Projector after the SR-1000 has powered down.