Loosen the fasteners (D) on the cable gland plate to remove the plate and close
the door.
Figure 5-7 Loosening the Fasteners
Remove the hexagonal nuts (E), spring washers (F), washers (G1), bolt (H),
and washers (G2).
Figure 5-8 Removing the Cabinet from the Pallet
Discard the pallet.
Lift the cabinet with the hoisting equipment at 500 mm (19.69") above the
foundation. Pull all the cables out of the foundation and guide the cables
through the base of the cabinet.
Carefully lower the cabinet on the foundation. Make sure that the cabinet is
aligned with the installation holes.
Remove the eyebolts (M16) on the top of the cabinet and seal the holes.
33

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the MaxiCharger DC Fast and is the answer not in the manual?

Questions and answers

Brian Hughes
March 5, 2025

How do I turn on our 120kW charger remotely, from https//uscloud.autelenergy.com/charging reality.

User image 67c7e6a70f307
1 comments:
Mr. Anderson
March 5, 2025

The Autel MaxiCharger DC Fast 120kW charger can be managed remotely using the Autel Charge Cloud. Through the cloud platform, you can access the charger status, monitor energy consumption, and manage user data. However, the specific steps for turning the charger on remotely are not provided in the available information.

This answer is automatically generated

Subscribe to Our Youtube Channel

Table of Contents

Save PDF