FIGURE 59 Crimping the power supply wire in the power lug
1
AWG power supply wire:
#8 AWG wire for 1200W power supply
#6 AWG wire for 1800W power supply
4.
Connect the -48V cable to the negative terminal and the 0V cable to the positive terminal on the power supply.
NOTE
DC return must be isolated from the router ground (DC-I) when connecting to the power supply.
5.
Replace the transparent cover.
This equipment installation must meet NEC/CEC code requirements. Consult local authorities for regulations.
Final steps
Complete these steps in the order listed:
•
"Attaching a management station"
•
"Activating the power source"
•
"Verifying proper operation"
Installing a Brocade MLX-32 router
The Brocade MLX-32 router can be installed on a 2-post Telco open frame rack or a 4-post enclosed rack or cabinet.
Preparing the installation site
Before installing the router, plan the location and orientation relative to other devices and equipment. For cooling purposes, allow a
minimum of six inches of space between the sides, front, and the back of the router and walls or other obstructions. If a router is installed
within a perforated enclosure, the perforations must cover at least 60 percent of the surface.
You will need to use a mechanical lift to move and install the router. Be sure to allow enough working room for the lift.
NOTE
Make sure your site provides 200-240 AC power.
Ensure that the proper power and network cabling is installed at the site.
For information on cabling, refer to
router"
on page 113,
"Attaching a management station"
Brocade MLX Series and Brocade NetIron XMR Installation Guide
53-1004195-02
DRAFT: BROCADE CONFIDENTIAL
"Brocade MLX-32 cable management"
on page 118, and
on page 103,
"Installing power supplies in a Brocade MLX-32
"Connecting the router to a network device"
Installing a Brocade MLX-32 router
on page 207.