Installing a NetIron XMR 16000 router

1
AWG power supply wire:
#8 AWG wire for 1200 W power supply
#6 AWG wire for 1800 W power supply
5.
Connect the -48V cable to the negative terminal and the 0V cable to the positive terminal as marked on the power supply.
NOTE
DC return must be isolated from the device ground (DC-I) when connecting to the power supply.
6.
Replace the transparent cover.
This equipment installation must meet NEC/CEC code requirements. Consult local authorities for regulations.

Final steps

Follow these steps to complete the installation:
"Attaching a management station"
"Activating the power source"
"Verifying proper operation"
Installing a NetIron XMR 16000 router
This section describes how to install a NetIron XMR 16000 router.

Preparing the installation site

Before installing the router, plan the location and orientation relative to other devices and equipment. For cooling purposes, allow a
minimum of six inches of space between the sides, front, and the back of the router and walls or other obstructions. If a router is installed
in a perforated enclosure, the perforations must cover at least 60 percent of the surface.
Ensure that the proper power and network cabling is installed in the site. For information on cabling, refer to
NetIron XMR 16000 router"

Unpacking a NetIron XMR 16000 router

The NetIron XMR 16000 router ships with the following items:
Router chassis with the appropriate number of switch fabric modules installed in slots marked SF, and slot blanks installed in all
empty slots.
Insertion or extraction tool for use with RJ45 and fiber-optic connectors.
If any items are missing, contact the place of purchase.
Follow these steps to unpack a NetIron XMR 16000 router.
1.
Remove the router from the shipping carton and all packing materials.
2.
Save the shipping carton and packing materials in case you need to move or ship the router at a later time.
152
on page 158, and
"Attaching a management station"
on page 184.
Brocade MLX Series and Brocade NetIron XMR Installation Guide
"Installing power supplies in a
53-1004195-02