07 Equipment Commissioning

7 Equipment Commissioning

7.1 Check Items Before Switching Power ON

No.
The inverter is firmly installed in a clean place where is well-ventilated and easy to
1
operate.
The PE cable, DC input cable, AC output cable, and communication cable are connected
2
correctly and securely.
3
Cable ties are routed properly and evenly, and no burrs.
4
Unused ports and terminals are sealed.
5
The voltage and frequency at the connection point meet the on-grid requirements.

7.2 Power On

Step 1 Turn on the AC switch between the inverter and the utility grid.
Step 2 Turn on the DC switch of the inverter.
PV
Power ON
2
1
Turn on
Inverter
3
The DC switch locking hole is for Australia only.
User Manual V1.1-2022-07-20
Check Item
1
AC Breaker
Power
distribution
cabinet
Power OFF
Turn off
34
Transformer
Grid
1
3