13. Adapting to another gas type
Modify the "min output" setting with the setting screw
See Table page 40.
13.2 Gas type
Affix the label which indicates for which type of gas the boiler is fitted
and set.
13.3 Eventual assembly of an external solenoid valve
All countries except Belgium:
For an installation located at least 1 metre below ground floor level, it
is necessary to fit an external solenoid valve to the gas supply pipe
close to the inlet to the buiding or premises.
For Belgium:
The boiler installation and gas connection must be carried
out by a qualified professional in compliance with the NBN
D 51.003, NBN D 30.003, NBN B 61.001, NBN B 61.002 and
NBN D 51.006 standards.
For an installation located at least 1 metre below ground floor level, it
is necessary to fit an external solenoid valve to the gas supply pipe
close to the inlet to the buiding or premises.
Electrical connection is done in the control panel using the alarm and
control module.
Alarm and control module AM35 (GR12).
68
.
Check the output delivered again.
Adjust if necessary.
For Switzerland: The maximum limit values authorised by the
OPAIR federal order on air protection regarding CO and NOx must
be checked using measurements made in the place of installation.
When the setting is correct, close the flap.
Switch the On/Off switch on Off.
Remove the measuring equipment.
Replace the plastic plug onto the measuring tube.
DTG(E)130 - 35/45/65/90/115 Eco.NOxPlus
15/02/2011 - 300014279-001-J