Commissioning

7.1

Commissioning procedure

7.2

Gas settings

Tab.37
Factory settings G20 (H-gas)
Code
Display text
DP003
Abs. max fan
DHW
GP007
Fan RPM Max
CH
GP008
Fan RPM Min
GP009
Fan RPM Start
7725131 - v.01 - 06062019
1. Open the main gas tap.
2. Open the boiler gas tap.
3. Switch the power on with the boiler's on/off switch.
4. Set the components (thermostats, control) so that heat is demanded.
7.2.1
The factory setting of the boiler is for operation with the natural gas group
G20 (H gas).
Description
Maximum fan speed on Domestic
Hot Water
Maximum fan speed during
Central Heating mode
Minimum fan speed during
Central Heating + Domestic Hot
Water mode
Fan speed at appliance start
7.2.2
Before operating with a different type of gas, carry out the following steps.
Warning
Initial commissioning must be done by a qualified installer.
If adapting to another type of gas, e.g. propane, the boiler must
be adjusted before it is switched it on.
See
Fan speed for different gas types, page 52
The start-up program will start and cannot be interrupted. During the
program, all segments of the display are shown briefly.
Important
In the event of an error during the start-up, a message with the
corresponding code is displayed. The meaning of the error codes
can be found in the error table.

Factory setting

Adjustment range
1000 Rpm - 7000 Rpm
1400 Rpm - 7000 Rpm
1400 Rpm - 4000 Rpm
1000 Rpm - 4000 Rpm

Adjusting to a different gas type

Warning
Only a qualified installer may carry out the following operations.
7 Commissioning
45
65
90
5400
5600
6300
5400
5600
6300
1550
1600
1600
2500
2500
2500
AMC Pro
115
6800
6800
1750
2500
51

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents