Equipment Commissioning; Check Items Before Switching Power On; Power On - Goodwe HT Series User Manual

Hide thumbs Also See for HT Series:
Table of Contents

Advertisement

User Manual V1.0-2022-05-04

7 Equipment Commissioning

7.1 Check Items Before Switching Power ON

No.
The inverter is firmly installed in a clean place where is well-ventilated and easy to
1
operate.
The PE cable, DC input cable, AC output cable, and communication cable are connected
2
correctly and securely.
3
Cable ties are routed properly and evenly, and no burrs.
4
Unused ports and terminals are sealed.
5
The voltage and frequency at the connection point meet the on-grid requirements.

7.2 Power On

Step 1 Turn on the AC switch between the inverter and the utility grid.
Step 2 Turn on the DC switch of the inverter.
PV
The DC switch locking hole is for Australia only.
Check Item
Inverter
3
07 Equipment Commissioning
1
AC Breaker
Power
distribution
cabinet
Power ON
Turn on
Power OFF
Turn off
33
Transformer
Grid
2
1
1
3

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Gw250k-htGw250kn-htGw225k-htGw225kn-ht

Table of Contents