The optional Main Power Meter (MPM-2) can be installed on the Main
Installing an
Power Supply (MPS-24A only). One scale on the MPM-2 provides an
Optional Main
indication in volts of the voltage across the batteries in the system. A
Power Meter
second scale indicates the battery charging current in amps. Complete the
following steps and refer to Figure 33 to install the MPM-2.
1. Remove the two screws in the bottom left-hand corner of the
2. Thread the two standoffs provided into the holes vacated by the two
3. Complete the installation of the MPM-2 by plugging the female
All manuals and user guides at all-guides.com
MPS-24A.
screws just removed. Place the MPM-2 assembly over the standoffs
and secure with the two original screws
connector on the meter cable into plug P7 on the MPS-24A.
Installation—Installing the FC-2000