Safety Checks - WAGNER Cobra 40-10/2K Translation Of The Original Operating Manual

High pressure double diaphragm pump for 2 component products with mixing ratio 1:1
Hide thumbs Also See for Cobra 40-10/2K:
Table of Contents

Advertisement

VERSION 07/2014
OPERATING MANUAL
Cable cross sections
Pump
Paint tank
Conveyor
Booth
Spraying stand
Procedure:
1 Screw on grounding cable with eye.
2 Clamp the grounding cable clip to a grounding
connection on site.
3 Ground the product (paint) tank to an on-site
grounding connection.
4 Ground the other parts of the system to an on-site
grounding connection.
6.7

SAFETY CHECKS

Carry out safety checks in accordance with Chapter 8.2.3.
Before every start-up, the following points should be observed:
-
Secure gun with safety clip.
-
Check the permissible pressures.
-
Check all connections for leaks.
-
Check hoses for damage.
It should be ensured that the device is in the following state before carrying out any
work on it:
-
The pressure should be released from the pump and high-pressure hose with gun.
-
The gun should be secured with the safety clip.
-
The air supply should be interrupted.
Pressure tightness test
For pressure tightness control of the entire installation, the fl ushing agent product
pressure is slowly increased step by step until the product pressure of the pump
indicated on the type plate is reached.
Overpressure!
Risk of injury from bursting components.
ORDER NUMBER DOC2349980
4 mm2;
6 mm2;
16 mm2;
16 mm2;
16 mm2;
WARNING
The operating pressure must not exceed the value shown on
the type plate.