7.

Decommissioning

Observe the safety chapter
Observe the basic safety instructions in the "Safety Instructions"
chapter.
In addition, observe all safety instructions in the manufacturer
documentation found in the appendix.
Secure the press from unauthorized reactivation after work is completed!
Only have the power supply disconnected by authorized personnel!
7.1

Switching off the press

Clear the press!
Switch off the optional components!
Disconnect the supply of operating materials (air)!
7.2

Shutting down the press (longer period of time)

Carry out the following storage measures if it is intended to decommission
the press for longer than 4 weeks!
Empty:
Disconnection of the energy sources:
Storage:
HKPL-DS
Translation of the original operating manual
Decommissioning
Drain condensate at the maintenance module
Remove parts
Power supply line (option)
Air supply line
Cover the press to protect it from contaminants
Slightly oil the bare metal parts to protect them from corrosion
Store the press on transport pallets
Fasten moving parts