ABB ACS2000 AFE 1MVA User Manual page 117

Medium voltage drives
Table of Contents

Advertisement

117
ACS2000 AFE 1MVA UM 3BHS297030 ZAB E01 REV. J
Motor
1.
Motor installed, aligned and alignment protocol available
2.
Motor not coupled to driven load
3.
Ground connection completed
4.
Motor auxiliaries (eg, bearing lubrication, heater cooling) ready
Insulation tests
1.
All power cables to input transformer, between input transformer and drive, and from drive to motor mea-
sured, measured values within the required limits.
2.
Report of the megger test available
If the test is carried out by the commissioning engineer of the drive, an additional day per drive motor
combination needs to be reserved. After the test, the feeder cables can be connected, except at the drive
end. The test must comply with the specification.
Power supply
1.
Medium voltage available for start-up of drive
2.
Low voltage auxiliary power available for start-up of drive
Miscellaneous
1.
Sufficient number and correct type of spare parts available
2.
Air conditioning of drive room ready for load run of drive
3.
Optional equipment ready

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents