Install The Ultraglide Sensors
Sensor mounting locations may be influenced by the boom configuration. Make sure that the sensors will not
interfere with or be damaged while folding or unfolding the booms. Locate an appropriate location for mounting
a sensor on the boom. The sensor should be mounted outside of the boom fold but inside of the boom
breakaway.
Note:
When mounting two sensors per boom, the inside sensor must be turned sideways in order to fold
the booms without the sensors interfering.
To Mount the Left and Right UltraGlide Sensors
Sensor Mounting Locations
FIGURE 10.
Mount the Sensor Mounting Bracket to the boom by installing the two U-bolts (P/N 107-0171-613) and four
1.
3/8" Lock Nuts (P/N 312-1001-164).
Repeat these steps to mount the remaining Right Sensor.
2.
Repeat these steps if dual sensor option was purchased.
3.
To Connect the Sensor Cables
Connect the Left Sensor Cable to the connector on the Left Sensor.
1.
Route the left sensor cable toward the AutoBoom Valve.
2.
Loop and tie-off any excess cable, while allowing enough excess cable for boom folding and extension.
3.
Repeat these steps to connect the right sensor cable.
4.
Manual No. 016-0230-012
UltraGlide
63