IBM Power775 Service Procedure page 78

Disk enclosure chassis service procedure
Hide thumbs Also See for Power775:
Table of Contents

Advertisement

6. Select BPC port for FDT
• If the lower BPA is not targeted for service, and is functional:
Plug the FDT UPIC cable into port T10 of the lower BPC.
• If the lower BPA is targeted for service, or is not functional:
Plug the FDT UPIC cable into port T10 of the upper BPC.
7. Login to the HMC with the User ID hscroot.
Use the HMC that is connected to the BPA where the FDT is plugged.
8. From the HMC left Navigation menu, expand Systems Management then select
Frames.
Verify frame serial number for the frame to be serviced.
9. In the Frames view on the HMC, place a checkmark in the Select column for the
frame to be serviced.
10. Verify that the frame Status is Rack Standby/Rack Standby or Standby/Standby.
• If frame Status reads Rack Standby/Rack Standby or Standby/Standby –
OK.
Continue to next step.
• If frame Status does not read Rack Standby/Rack Standby or
Standby/Standby – action required. Contact next level of support.
11. From the Task menu on the HMC, select Serviceability > Hardware > Fill and
Drain Tool Tasks > Fill and Drain Command Interface
Power775 Disk Enclosure Chassis Service Procedure
----Appendix A: DE Pressure Test Procedure ----
Page 78 of 171