VVR - MANUAL
STEP 6B
DUAL (V-type Base Channels):
Align the front edge of the VVR 2.25 inches from the control arm (as mentioned in the
steps above (STEP 2).
Align VVR baseplate onto base channels such that the angled portion of the base plate
sits flush against the base channel and the 2 crank arm assemblies are positioned
approximately in-line with the 2 control arms. The linkage will must be attached to the
center control arm by sliding the linkage through the hole and fastening it with the nut.
Crank Arm Assemblies
STEP 7
Mount the PACE, FHC, or LMX.
For PACE mounting proceed to Step 8.
For FHC mounting proceed to Step 9.
For LMX mounting proceed to Step 10.
STEP 8
To mount the PACE, install 3 self-tapping screws. Two for the holes on the right hand side of
PACE and one for the left hand side.
To mount the PACE in the correct location please follow steps 8A-8C.
NOTE:
Self-tapping screws are not provided with the VVR. The recommended size is a 3/8"
self-tapping screw for metal.
STEP 8A
Mount the PACE below the top tab insert on the encloure. There must be a minor gap so the
lid of the enclosure can slide on after.
17 | VVR– Manual | AntecControls.com