Backleak Audit With Magmah v9.01 onwards (If optional backleak measurement unit is
fitted)
Refer to figure 5.5
Specific note for pressurised backleak units:
Before starting an audit the following should be disconnected:
a) the extraction tube hydraulic connection (5
degree push-fit elbow)
These must be re-connected after the audit.
A single (CRi 1-line) or set of four (CRi 4-line) good injector(s) should be used for the
backleak unit audit. The purpose of the audit is to check the following three features of the
backleak unit:
-
measurement line transducer offsets (step 2)
measurement line 'max fill' calibration values (step 4)
-
-
measurement system leakage (step 5)
If the audit indicates a problem in any of these areas, please contact Hartridge for further
assistance.
1. Select F10 from the Alternate Menu to bring up the Backleak Audit dialog box.
2. Select [Load Testplan] and load any testplan for the injector type fitted.
3. Start the main motor and then press [Start] to start Step 1 of the audit. This applies the
pressure, pulse width, and speed demands shown in the dialog box.
96
THIS IS AN UNCONTROLLED DOCUMENT downloaded by Lukas Matuska on 16 Feb 2016
Any technical intervention requires certified Hartridge training. Contact Hartridge Ltd for details.
th
port; disconnect the 6mm pipe from the 90
a
HARTRIDGE LIMITED
HL037 (EN), Issue 13, AT714, 05/14

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents