OverView D 50" – DOC-3303-5 – installation manual – Revision 10 – September 2006
2 screws
0 screws
2 screws
0 screws
static
10 screws
8 screws
September 2006 ________________________________
September 2006
September 2006
3. Installation of Screen Module
All screens are delivered with full movability,
i.e. no screws attached.
The number of screws to be applied and fixed
depends on the position of the screen in the
display wall.
Depending on the position of the screen in the
display wall, zero, 8 (4x2), 2 (2x1) or
10 (4x2 + 2x1) screws have to be installed.
Please note:
Installation of the screens starts on the bottom
row.
Every darkbox provides the fixation facilities for
the screen. The fixation facilities comprise 4
screw connectors (one at each corner), and in
addition next to the top screw connectors a
guide pin to put on the screeen.
The fixation facilities and their use are the
same for the screen modules and the seamless
screens.
Start installing the static screen:
The static screen is the screen in the mid of the
bottom row.
In case of an even number of colums (no
"center module") the static screen is the first
screen of the right half of the display wall,
seen from front.
For the static screen, apply and fix all 10
screws: both, movability in vertical and in
horizontal direction has to be locked!
_________________________________________________________
________________________________
________________________________
Step1
Step2
_________________________ 3-6
_________________________
_________________________

Advertisement

Table of Contents
loading

This manual is also suitable for:

Overview mdg50-dlOverview mdr50-dlOverview mdr+50

Table of Contents