Figure 10. Connecting the rear power cords
Preparing the system for operation after removing and replacing a line cord conduit from
the 9080-M9S system node
To prepare the system for operation after removing and replacing a line cord conduit, complete the steps
in this procedure.
Procedure
If the customer required the system to be powered off to complete the repair, have the customer perform
the following steps. If the customer did not require the system to be powered off, no additional steps are
necessary.
a) To power on the system, from the Operation list, select System Level Activate. Then, click OK to
confirm the operation.
b) To restart the logical partitions, complete the following steps:
1) In the navigation area, click the Resources icon
2) Click the system name in which you want to activate the logical partition.
3) Select the logical partition name that you want to activate.
, and then click All Systems.