Figure 188. Replacing the front screws
4. Review the following information to identify the locations where each SMP cable connects to the
system node that you are servicing. Then, refer to your labels and the following steps to reconnect
the SMP cables that you removed from the system node you are servicing.
• If you have a two node system configuration, use Figure 189 on page 217 and Table 26 on page
217 to determine the point-to-point cabling for SMP cables.
216 Power Systems: Removing and replacing parts in the 9080-M9S system