UPS5000-E-(25 kVA-75 kVA)-SM
User Manual (Half Height)
Step 3 Set Sched. shallow dis. test time, Sched. shallow dis. test interval and Shallow dis. test dis.
ratio (%). After setting is complete, the system will perform automatic shallow discharge
tests based on the settings.
Figure 5-10 Automatic shallow discharge settings
----End
Manual Shallow Discharge Test
Step 1 Log in to the WebUI.
Step 2 On the Monitoring > Control > System Commands and Tests page, click Start next to
Shallow discharge test to start a shallow discharge test.
Issue 03 (2019-12-13)
Copyright © Huawei Technologies Co., Ltd.
5 Operations
140