2. Use insulated tools during installation and operation. 3. Only Huawei engineers or engineers certified by Huawei are allowed to install, commission, and maintain the UPS. Otherwise, personal injury or equipment damage may occur, and the resulting UPS faults are beyond the warranty scope of Huawei.
Page 3
6. Remove the four rubber plugs from the 7. Insert four M12x115 expansion bolts into bottom of the cabinet (two on the front and the expansion bolt holes in the floor, and two at the back). tighten the expansion bolts. Non-Secured Installation 1.
Connecting Cables 1. This document describes cable routing by removing the top cover when there are two mains inputs. 2. In the case of single mains, you do not need to connect bypass input power cables and remove short-circuit copper bars. UPS Cable Connection Reference •...
Page 5
Connecting Cables Connecting Cables to the UPS5000-E-200K-SM 2. Remove the cover from the power Scenario 1: Routing Cables from the Top distribution subrack. 1. Remove the small covers of the cabinet top. The cover can be opened only if the maintenance bypass switch is OFF.
Page 6
5. Connect the mains input cables to mains input 6. Connect the output power cable. power distribution terminals 1L1, 1L2, and 1L3, respectively. Connect the bypass input cables to bypass input power distribution terminals 2L1, 2L2, and 2L3, respectively. Connect the N wires of the mains and bypass input cables to the input power distribution terminal N.
Page 7
8. Connect signal cables. Scenario 2: Routing Cables from the Bottom 1. Remove the cover from the power distribution subrack. The number and 2. Remove the copper bars between mains color of signal input terminals and bypass input terminals. cables in the figure 3.
Page 8
Connecting Cables to the UPS5000-E-200K-FM Scenario 1: Routing Cables from the Top 1. Remove a certain number of small covers 2. Remove the cover from the power from the top of the cabinet based on site distribution subrack. conditions. 3. Remove the copper bars between mains 4.
Page 9
5. Connect the mains input power cable. 6. Connect the bypass input power cable. Route a neutral wire from the middle of the 7. Connect the battery cable. positive and negative battery strings. Take a battery string consisting of 40 batteries as an example.
Page 10
8. Connect the output power cable. 9. Connect signal cables. Scenario 2: Routing Cables from the Bottom A cable entry cabinet needs to be installed when cables are routed from the bottom. This document uses the cable entry cabinet installed on the right of the UPS cabinet as an example. 1.
Page 11
5. Place the cable entry cabinet on the right of 7. (Optional) Secure the cable entry cabinet to the UPS cabinet. the ground. 6. Install the front and rear connecting kits. 8. Install an equipotential plate. 9. Remove a certain number of small covers 10.Remove the signal cable trough cover from from the bottom of the cable entry cabinet the cable entry cabinet.
11.Connect signal cables. 12.Connect power cables. NOTE For the screw specifications and torque used The figure shows the signal cable routing and for connecting cables in a bottom cable is for reference only. Connect the cable based routing scenario, refer to the top cable on the actual situation.
Close the upstream bypass and mains input switches. (Full configuration model) Close the UPS bypass input switch, output switch, and mains input switch. After the UPS is powered on, initialization begins. The MDU displays the Huawei logo and an initialization progress bar.
Page 14
Initial Startup • If the UPS is powered on for the first time, you need to obtain the startup password from the Service Expert app. Skip this step if the UPS is not powered on for the first time. • The Service Expert app can be downloaded from Google Play Store and can run on Android.
Page 15
3. After you perform the settings, the Bypass mode and No battery alarms are reported by the MDU and do not need to be cleared. If there is any other alarm, you need to rectify the fault. 4. View the system running status diagram on the MDU to check that the UPS is working in bypass mode.
Powering On Loads 1. After the inverter starts, the UPS works in normal mode. The Bypass mode alarm disappears from the MDU. 2. After confirming that the battery strings are properly connected, turn on the battery string input circuit breaker. If there are multiple battery strings, turn on the circuit breaker for each battery string and then turn on the general circuit breaker between battery strings and the UPS.
Page 17
Scan here for technical support (carrier): Huawei App Store Scan here for more documents: Support-E Support WeChat You can also log in to Huawei technical support website: http://support.huawei.com/enterprise http://support.huawei.com Huawei Technologies Co., Ltd. Huawei Industrial Base, Bantian, Longgang Shenzhen 518129 People's Republic of China...