Step 2 On the Monitoring > Control > System Commands and Tests page, click Start next to
Forced equalized charging to start a forced equalized charging test.
Figure 5-9 Starting a forced equalized charging test
----End

5.1.6.2 Shallow Discharge Test

Before conducting a shallow discharge test, check whether the requirements of a shallow
discharge test are met. If the requirements are met, the button for starting a shallow discharge
test is available. Otherwise, the button is unavailable.
Before a shallow discharge test, ensure that:
Automatic Shallow Discharge Test
Step 1 Log in to the WebUI.
Step 2 On the home screen of the WEBUI, choose Monitoring > Param. Settings > Battery
Param., and set Sched. shallow dis. test to Enable.
Issue 03 (2019-12-13)
Click Stop next to Forced equalized charging in any of the following cases:
The forced equalized charging test duration reaches the forced equalized charging protection time
(12–24 h, 18 h by default).
The UPS generates a battery overtemperature, overvoltage, or overcurrent alarm.
An alarm is generated.
The UPS works in normal mode with a load ratio fluctuation less than 10%.
The UPS has generated no battery overtemperature, overvoltage, or overcurrent alarm. No
generator is connected to the UPS.
The mains, batteries, charger, and discharger are normal. No overload alarm is generated.