Installation Checklist

The mechanical and electrical installation of the DCS800-A should be checked
before start-up. It is advisable to go through the checklist below together with
another person. Study carefully the
manual before attempting any work on, or with, the unit.
MECHANICAL INSTALLATION (see chapter
The ambient operating conditions are acceptable, e.g. environmental conditions and fan data in
the DCS800 Hardware Manual (3ADW000194) and free space requirements in chapter
Mechanical
Installation.
The unit is mounted properly.
Cooling air will flow freely:
o the lifting bars (if used) are removed,
o the cabinet roof is attached properly,
o the filters (if used) are mounted properly,
o the D6 / D7 modules (if used) air outlet is connected properly,
o the air baffle plates of the converter modules are mounted properly.
ELECTRICAL INSTALLATION (see chapter
Joining of the shipping splits:
o the AC busbars and PE busbars are properly connected (see chapter
Installation),
o the internal control cables are properly connected.
The converter units and cabinets are grounded properly.
The mains voltage matches the DC converter nominal input voltage.
The setting of the internal 220 VAC /115 VAC transformer T2 corresponds to the supply voltage.
The mains (input power) connections at U, V and W (L1, L2 and L3) are OK.
The appropriate mains fuses are installed for units D1 to D4, see DCS800 Hardware Manual
(3ADW000194).
Motor cable routing (armature and excitation) is OK.
Check that the screens are properly installed at the motor and in the drive cabinet.
Installation Checklist
Safety Instructions
Installation Checklist
Mechanical
Electrical
Installation)
3ADW000352R0101 DCS800-A Installation Manual e a
at the beginning of this
Installation)
Mechanical

Advertisement

Table of Contents
loading

This manual is also suitable for:

Dcs800-a

Table of Contents