ABB DCS800 Series Installation Manual page 21

Enclosed converter
Hide thumbs Also See for DCS800 Series:
Table of Contents

Advertisement

21
② Remove the lifting bars (if used) and the lifting
lugs (only for marine applications). Refasten the
500 mm from ceiling
original bolts or upper vibration dampers (only for
marine applications) in order to maintain the
degree of protection of the cabinet.
③ Fasten the first shipping split to the next
shipping split. See section
Joining the shipping
splits. Each shipping split includes a 200 mm
joining cabinet.
④ Fasten the second shipping split to the floor.
⑤ Connect the AC busbars and the PE busbar.
See section
Connecting the AC Busbar and the
PE
Busbar.
⑥ Reinstall the roof if they have been removed.
Attach each roof with 6 screws M6.
Working order installation
Mechanical Installation
3ADW000352R0101 DCS800-A Installation Manual e a