5.1

OPERATION - PROCEDURES

5.1.1

START-UP PROCEDURE

WARNING!
Situation of UPS-System before switching it on:
1.
Make sure the fuses for the supply of UPS-System in the Input Distribution Board on site are open.
2.
Make sure all the input and output cabling has been performed correctly.
3.
Verify that the Parallel Isolator Switch IA2 is open (Position OFF).
4.
Verify that the Maintenance Switch IA1 is open and in Position OFF.
5.
Make sure that the internal battery enclosure fuses and/or the external battery cabinets fuses are
open.
6.
Bypass fuses F2 and rectifier fuses F1 are inserted.
Start up procedure of PowerScale:
1.
Insert fuses for the supply of UPS-System in the Input Distribution and check the input phase
rotation.
- The LED-indicators LINE 1 and battery on UPS-Module is lit – green
- On LCD-Display "LOAD OFF, SUPPLY FAILURE" will appear.
2.
UPS 1:
Press both "ON/OFF" Main Buttons to switch on UPS.
LCD panel must display: "LOAD DISCONNECTED PARALLEL SWITCH OPEN" and the LED-
indicator will appear as shown below:
LED Indicator
LINE 1
LINE 2
BYPASS
INVERTER
BATTERY
3.
Check Command: LOAD TO INVERTER
LED indicator will appear as shown below:
LED Indicator
LINE 1
LINE 2
BYPASS
INVERTER
BATTERY
4.
Scroll through the menu measurement and check their correctness
5.
Check battery polarity and voltage.
THE OPERATIONS DESCRIBED IN THIS CHAPTER MUST BE PERFORMED BY A
SERVICE ENGINEER FROM THE MANUFACTURER OR FROM A AGENT
CERTIFIED BY THE MANUFACTURER.
Colour
Green
Green
Green
OFF
Flashing Green
Colour
Green
Green
OFF
Green
Flashing Green
04-3004_S5_OPM_ABB_POWERSCALE_10-50kVA_EN_150113.doc
Printed in Switzerland – Modifications reserved
Section-5
Page 2/6 ABB

Advertisement

Table of Contents
loading

This manual is also suitable for:

Powerscale cabinet bPowerscale cabinet c

Table of Contents