Transport, Installation And Start-Up; Transporting The Gas Pressure Regulator - Honeywell HON R100NG Series User And Maintenance Manual

Gas pressure regulator with pilot
Table of Contents

Advertisement

5
Transport, installation and start‐up 
Contents 
5.1
Transporting the gas pressure regulator 
Heavy transport units 
Suspended loads 
Selecting the hoisting 
equipment and slings 
User manual for HON R100 gas pressure regulator with HON P095NG pilot 
 
Topic 
Transporting the gas pressure regulator 
Installing the gas pressure regulator 
Installing the device connections 
Checking the system for leaks 
Starting up the gas pressure regulator 
 
 
Risk of serious injury posed by heavy loads when using cranes for transportation 
Transporting heavy devices or components with a crane may result in serious impact and 
crush injuries if the loads start moving in an uncontrolled manner. 
 Loads may only be transported with a crane by a duly qualified person. 
 Markings and information about the center of gravity of the load (if applicable) must be 
observed. 
 Loads may only be moved under supervision. 
 
 
Risk of serious injury in the event that load handling attachments break while holding a 
suspended load 
Heavy loads picked up or transported with hoisting and slinging gear may result in serious 
impact and crush injuries if the load handling attachments fail. 
 Only fasten the device at the positions intended for the transport. 
 The load‐bearing capacity of the appropriate hoisting equipment must correspond at 
least to the weight of the load to be transported. 
 Always stand clear of suspended loads. 
 Ensure that no person is within the danger zone. 
 
A mobile workshop crane is suitable for use as hoisting equipment. A pallet jack or forklift is 
also suitable for intraplant transportation. 
The following are adequate for use as slings: 
 Ropes 
 Belts 
 Chains 
The hoisting equipment and slings must meet the following criteria: 
 The load capacity must be sufficient for the gas pressure regulator's weight. 
 The hoisting height is adequate for the mounting position at the installation site. 
 
Transport, installation and start‐up 
 
Page
32
33
35
36
37
32 

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Hon p095ng seriesHon r100ngHon r100ng-foHon p095ng-mpHon p095ng-hp

Table of Contents