4.6 Unpacking

Move the equipment in it's original packing, carton box or wooden case, until the place of installation and remove
the packing and the transport sockets only just before installing the UPS.
Be aware of the heavy weight of the UPS, pay attention when moving the UPS cabinet.
White color
Red color
Fig. 4.6-1 ShockWatch device
Fig. 4.6-2 TiltWatch device
Note!
Be aware of the heavy weight of the UPS, pay attention when moving the UPS cabinet.
Take care not to damage the UPS when moving by forklift.
A damaged UPS must never be installed or connected to Utility or Battery!
In case of any damage sustained during the transport, immediately inform the shipping agent!
A detailed report of the damage is necessary for any indemnity claim.
Included in the delivery you can find the following parts:
· An accessory bag.
· Lower closures with air inlet grids, which must be mounted on the bottom of the cabinet UPS with the screws
included.
· Bus bars interconnection "Power Section cabinet" and "In/Out Module cabinet" with the screws included.
· Junction metal to connect "Power Section cabinet" and "In/Out Module cabinet" with the screws included.
· Control Bus cables for inter-connecting the UPS modules (only for the RPA Parallel System).
· The documentation includes the "Installation Guide & User Manual" and the "UPS Safety Rules".
Packing material recycling
ABB, in compliance with environment protection, use only environmentally friendly material.
UPS packing materials must be recycled in compliance with all applicable regulations.
=
without any anomaly
=
anomaly evidence
The package of the MegaFlex 1000 to 1600 is equipped with
ShockWatch (indicator for shock) and TiltWatch (indicator for
overthrow) on the outside.
These devices indicate an eventual shock or overthrow during
transport.
MegaFlex 1000 to 1600
Note!
Whenever these devices show a possible anomaly, the
UPS shall not be commissioned before consulting an
ABB Service Centre.