Standing Floor - ABB MegaFlex 1000 UL S1 Installation Manual

Hide thumbs Also See for MegaFlex 1000 UL S1:
Table of Contents

Advertisement

17/54

4.4.5 Standing floor

Make sure standing floor (especially in case of raised floor) has sufficient weight loading capability to tolerate the
UPS and extra weight that might occur from time to time.
The UPS must be installed on concrete or another non-combustible surface.
MegaFlex 1000 to 1600
MGF_UL_1000-1600_S1_UPS view top_01US
Power Section cabinet
Fig. 4.4.5-1 MegaFlex 1000 to 1600 – Opening on top of the cabinet for input and output cables connections
MGF_UL_1000-1600_S1_UPS view bottom_01US
Power Section cabinet
Fig. 4.4.5-2 MegaFlex 1000 to 1600 – Opening on bottom of the cabinet for input & output cables connections
MegaFlex 1000 to 1600 openings are provided on the top (*) and the bottom (*) of the UPS cabinet for the
connection of input and output cables.
Pay attention to the position of these openings, when choosing the placement of the UPS.
These openings are covered with a protective plate.
*) Please remove the plate before drilling any holes (see Fig. 4.9-2).
Opening for input and output cable connections
107.44" / 2729mm
129.92 " / 3300 mm
108.11 " / 2746mm
129.92 " / 3300 mm
MegaFlex 1000 to 1600
In/Out Section cabinet
Frontal side
In/Out Section cabinet
Frontal side
UPS Installation Guide / REV-A
1.04 "
26.5 mm
Opening on top
Opening on top
for input & output
for input & output
cables connections
cables connections
2.70 "
68.5 mm
1.26 " / 32 mm
21.22 " / 539 mm
Opening on bottom
for input & output
cables connections
1.97 " / 50 mm
19.84 " / 504 mm
2.72 "
69 mm
3.50 "
89 mm