ABB MegaFlex 1000 UL S1 Installation Manual page 11

Hide thumbs Also See for MegaFlex 1000 UL S1:
Table of Contents

Advertisement

11/54
Fig. 2.1-5 MegaFlex 1000 to 1600 - General view without protection panels
1
Opening for top cable entry (please remove the plate before drilling any holes)
2
Opening for bottom cable entry (please remove the plate before drilling any holes)
3
Bus bars for Utility input connection
4
Bus bars for Load output connection
5
Bus bars for External Battery connection
CI
Customer Interface Board (see Fig. 2.1-4)
CR
Connectivity Rack
J35DSP Serial port RS232 (only for ABB Service Center)
J35µP
Serial port RS232 for IMV protocol
RPA
RPA board (Redundant Parallel Architecture) for Parallel System (option - see Fig. 2.1-2)
SNMP
3-ph SNMP/WEB plug-in adapter (option - see Fig. 2.1-4)
XA
Terminal block (see Section 4.11)
Caution!
Convenience test terminals are available for ABB Service Technician only.
Unauthorized access to test terminals exposes to electric shock hazard risk and increases risk of
UPS failure.
MegaFlex 1000 to 1600
UPS Installation Guide / REV-A
1
4
5
3
2