MODULAR SAFETY INTEGRATED CONTROLLER MOSAIC
Result of the simulation
The graph shows the signals relating to the simulation, in this case:
which indicates closing of the gate.
which indicates the request to start sent by the operator
have elapsed
logic level 1.
The AND operator output signal is delayed by 2000 ms by the delay operator.
The "Op7" retarder output signal sends the command to close the relay when
5000 ms have elapsed, at which time the "M-press" relay is activated.
Figure 101 - Graph produced by the simulation of the application example
8540780 • 10/07/2020 • Rev.38
233