Installing the Panel

• Choose the best location for the panel position, with an ambient temperature between
0°C and 40°C., away from heating sourses, environmental dust and potential water
ingress.
• Remove all packaging.
• Inspect visually the panel for any damage.
• Remove the outer cover, by unscrewing the two allen screws. Stow the cover in a
safe position.
• Inspect the internal PCB and make sure the internal components are firmly in place.
• Observe the main PCB chassis and the associated securing screw, located in the
front of the terminal blocks.
• Unfasten the chassis securing screw and remove the chassis. Stow in a safe location.
• Choose which cable entry points to knock out and carefully remove the knock-outs.
• Observe the top center fixing location at the back of the panel.
• Stow the back box in a safe position.
• Drill the wall to suit the back box center fixing position, plug and insert a fixing
screw.
Note: If you are installing MAG 4 in plastic box use the template on the back side of
the packaging box to drill the mounting holes on the wall.
• Temporally hang the back box from the fixing screw and mark out the two bottom left
and right fixing locations.
• Remove the back box from the center fixing screw position and drill and plug the
bottom fixing holes.
• Hang the back box from the center fixing position and fix securing screws through
the bottom fixing holes.
• Tighten all the fixing screws.
• Route the external cables onto the back box, make off connection glands etc., DO
NOT make any connections at this stage. ENTER THE MAINS CABLE THROUGH
ITS OWN CABLE ENTRY POINT AND KEEP MAINS WIRING AWAY FROM SYSTEM
AND OTHER LOW VOLTAGE WIRING.
• Re-fit the PCB chassis and re-connect the chassis mains connection.
• Connect the mains supply and earth to the main terminal block. DO NOT switch on
the main electrical supply at this stage.
• Position the battery in an upright position.

Testing the Panel

ATTENTION: It has been assumed that prior to making the connection
!
at the panel, the integrity of the system ALL wiring has been
comprehensively tested, including insulation to earth.
• Connect the battery leads from the black power supply box to the positive and
negative battery terminals.
• Switch on the mains power supply.
• If the buzzer and indicator LED's are operating, press the RESET button.
In Normal Operating Mode only POWER SUPPLY 230V will be illuminated.
If in the Normal Operating Mode other LED's are illuminated and the buzzer is sounding,
carefully check all fuses and connections. Refer to the part of the internal connections
or circuitry the associated yellow LED's apply to. The connection diagram on the inside
of the external cover will assist in identifying the LED.
!
NOTE: The battery might show a 'Low Battery Fault' initially until it has had
time to charge up to the required level.
6
Fire Control Panel MAG 4 - User Manual