Replace the peripheral board

To replace the peripheral board, refer to
Figure 12-5: Replacing the Peripheral Board
A. Peripheral board
B. Ribbon cable (to motherboard)
C. Cable tie
D. TEC board ribbon cable
E. 12 V power wiring harness
F. M3 flat washer
G. M3 spring washer
H. M3 x 6 mm socket head cap screw
I. Relay wiring harness
J. Gas/cell temperature monitoring harness
K. Gas/cell temperature monitoring harness
L. Gas/cell temperature monitoring harness
Procedure
1. Shut down the analyzer.
Rosemount CT5100
Refer to
Shutdown
procedure.
Figure 12-5
and complete the following steps.