During handling work:
Remove all sources of voltage to the equipment: the grid, the PV array and any auxiliary power supply.
After setting the AC thermomagnetic and DC circuit breaker to OFF, wait at least 10 minutes before
opening the door. Internal capacitances may still hold hazardous voltages.
Once the equipment is open, check there is no electrical hazard in the voltage inputs from the grid,
the PV array or any auxiliary supply.
When checking that there is no voltage, wearing dielectric gloves and safety goggles approved for
electrical hazards is required.
AAS2000IKI01
Panel circuit breaker
Ingeteam Power Technology, S.A.
Grid connection thermomag-
netic circuit breaker
29